兰万灵在竞争二期LRT合同中多处作弊

lindamy

时代广场舞照跳
VIP
注册
2005-11-23
消息
30,363
荣誉分数
7,477
声望点数
373
Fatally flawed: The glaring weaknesses of SNC-Lavalin’s winning bid for Stage 2 of LRT

Ted RaymondNewstalk 580 CFRAPublished Friday, January 24, 2020 10:04AM ESTLast Updated Friday, January 24, 2020 11:50AM EST

SNC Lavalin

Pedestrians walk past the offices of SNC Lavalin, in Montreal, March 26, 2012. THE CANADIAN PRESS/Ryan Remiorz

OTTAWA -- Newly released documents show just how flawed SNC-Lavalin’s ultimately successful bid to extend the Trillium Line in Stage 2 was before the City pushed ahead with it.

In August 2019, the City revealed the SNC-Lavalin-backed TransitNEXT bid did not meet the required 70% technical threshold to advance in the bidding process. It moved ahead because City Staff had the discretion to allow a bid to advance to the financial evaluation phase despite the lower technical score.

But in a release of documents, sent around 9:00 p.m. Thursday, the full extent of the many, glaring weaknesses in SNC-Lavalin’s bid became clear.

In a technical evaluation submitted Oct. 3, 2018, the Technical Evaluation Team unanimously rejected the TransitNEXT bid.

“The proposal failed all four technical categories,” the evaluation said.

It described a lack of a defined signaling and train control system solution, “which ultimately affects the vehicle integration, the project schedule, and the overall success of the project.”

The bid was described as “generic” and “poorly written.” In two of the four technical categories, not a single “strength” was listed.

“Poor technical submission throughout (civil, track, stations, systems and vehicles). Use of sweeping motherhood statement that demonstrated a limited understanding of the project, were often contradicted and/or not backed up,” the Team said in a summary of the bid, which it said had fatal flaws.

“Resolving all of the major issues identified in the submission would be a lengthy and likely impractical process,” the evaluation said. “The significant scope discrepancies should cast doubt on the validity of the overall proposal. The extent of rework would be significant.”

It also said resumes of several key individuals were poor. The Maintenance and Repair director had no previous experience working on a relevant maintenance site; the Design Manager appeared to lack relevant experience; the Systems Integration Manager had no experience in the proposed role, but significant industry experience otherwise; and the Communications and Stakeholder Engagement Director had no project experience and only seven years of experience overall.

The City asked for a second evaluation of the three bids, with several questions from the Bid Evaluation Steering Committee.

When it comes to TransitNEXT, the Technical Evaluation Committee explained some of its issues further.

“The submission does not comprehensively address nor explain the critical path to substantial completion,” the TEC said.

The TEC described a proposal that contains inaccurate information, “such as references to elements that do no form part of the project scope of work, e.g. a catenary system and Traction Power Substations.” The Trillium Line does not run on a catenary system like the Confederation Line does.

“This demonstrates that the Proponent lacks understanding of the scope of works.”

The bid ultimately moved ahead to the financial evaluation phase anyway, because City staff had the discretion to allow a failed technical bid to still be evaluated on its financial merits.

In a memo, Director of Rail Construction Michael Morgan reminded Council the aggregate technical and financial scores were ultimately used to rank submissions and the team with the lowest technical score (TransitNEXT) had the highest aggregate score.

In other words, the SNC-Lavalin bid won because it was the cheapest one.

Morgan claims the decision to move the failing technical bid forward “was appropriate and is in the best interests of the City and taxpayers.” Morgan added the identities of all three bidders were not disclosed before this decision was made.

The $4.66-billion Stage Two contracts were passed March 6, 2019, during a heated City Council meeting, by a vote of 19-3. Only Councillors Diane Deans, Rick Chiarelli, and Shawn Menard voted against it. The Trillium extension portion of Stage Two costs $1.6-billion.

Morgan says meetings were held with SNC-Lavalin to resolve issues before the winning bid was presented to Council.

“Following the ranking, a series of meetings were held with the First Negotiation Proponent (FNP) to resolve all technical concerns noted during the technical evaluation process,” Morgan said. “Following resolution of all concerns, the FNP was designated the Preferred Proponent and presented to Council for approval. As stated by the Auditor General, all technical requirements of the RFP were met.”

Michael Morgan was one of the five people on the Technical Evaluation Team in 2018. He was the City's director of rail operations at the time. The other team members include two egineering consultants: Lead Evaluator Peter Schwartzentruber and Jack D'Andrea; and two City officials: manager of rail systems Russ Hoas, and Colleen Connelly, OC Transpo's manager of service planning.

The Trillium Line extension, which moves the north-south line from Greenboro to the Airport and Riverside South, is currently under construction. It’s slated to be complete by 2022.
RELATED IMAGES

  • O-Train
    The Technical Evaluation Team noted SNC-Lavalin's bid included inaccurate references to an overhead catenary system on the Trillium Line, despite the trains being diesel-powered.
 
最后编辑:
Fatally flawed: The glaring weaknesses of SNC-Lavalin’s winning bid for Stage 2 of LRT

Ted RaymondNewstalk 580 CFRAPublished Friday, January 24, 2020 10:04AM ESTLast Updated Friday, January 24, 2020 11:50AM EST

SNC Lavalin

Pedestrians walk past the offices of SNC Lavalin, in Montreal, March 26, 2012. THE CANADIAN PRESS/Ryan Remiorz

OTTAWA -- Newly released documents show just how flawed SNC-Lavalin’s ultimately successful bid to extend the Trillium Line in Stage 2 was before the City pushed ahead with it.
In August 2019, the City revealed the SNC-Lavalin-backed TransitNEXT bid did not meet the required 70% technical threshold to advance in the bidding process. It moved ahead because City Staff had the discretion to allow a bid to advance to the financial evaluation phase despite the lower technical score.

But in a release of documents, sent around 9:00 p.m. Thursday, the full extent of the many, glaring weaknesses in SNC-Lavalin’s bid became clear.

In a technical evaluation submitted Oct. 3, 2018, the Technical Evaluation Team unanimously rejected the TransitNEXT bid.

“The proposal failed all four technical categories,” the evaluation said.

It described a lack of a defined signaling and train control system solution, “which ultimately affects the vehicle integration, the project schedule, and the overall success of the project.”

The bid was described as “generic” and “poorly written.” In two of the four technical categories, not a single “strength” was listed.

“Poor technical submission throughout (civil, track, stations, systems and vehicles). Use of sweeping motherhood statement that demonstrated a limited understanding of the project, were often contradicted and/or not backed up,” the Team said in a summary of the bid, which it said had fatal flaws.

“Resolving all of the major issues identified in the submission would be a lengthy and likely impractical process,” the evaluation said. “The significant scope discrepancies should cast doubt on the validity of the overall proposal. The extent of rework would be significant.”

It also said resumes of several key individuals were poor. The Maintenance and Repair director had no previous experience working on a relevant maintenance site; the Design Manager appeared to lack relevant experience; the Systems Integration Manager had no experience in the proposed role, but significant industry experience otherwise; and the Communications and Stakeholder Engagement Director had no project experience and only seven years of experience overall.

The City asked for a second evaluation of the three bids, with several questions from the Bid Evaluation Steering Committee.

When it comes to TransitNEXT, the Technical Evaluation Committee explained some of its issues further.

“The submission does not comprehensively address nor explain the critical path to substantial completion,” the TEC said.

The TEC described a proposal that contains inaccurate information, “such as references to elements that do no form part of the project scope of work, e.g. a catenary system and Traction Power Substations.” The Trillium Line does not run on a catenary system like the Confederation Line does.

“This demonstrates that the Proponent lacks understanding of the scope of works.”

The bid ultimately moved ahead to the financial evaluation phase anyway, because City staff had the discretion to allow a failed technical bid to still be evaluated on its financial merits.

In a memo, Director of Rail Construction Michael Morgan reminded Council the aggregate technical and financial scores were ultimately used to rank submissions and the team with the lowest technical score (TransitNEXT) had the highest aggregate score.

In other words, the SNC-Lavalin bid won because it was the cheapest one.

Morgan claims the decision to move the failing technical bid forward “was appropriate and is in the best interests of the City and taxpayers.” Morgan added the identities of all three bidders were not disclosed before this decision was made.

The $4.66-billion Stage Two contracts were passed March 6, 2019, during a heated City Council meeting, by a vote of 19-3. Only Councillors Diane Deans, Rick Chiarelli, and Shawn Menard voted against it. The Trillium extension portion of Stage Two costs $1.6-billion.

Morgan says meetings were held with SNC-Lavalin to resolve issues before the winning bid was presented to Council.

“Following the ranking, a series of meetings were held with the First Negotiation Proponent (FNP) to resolve all technical concerns noted during the technical evaluation process,” Morgan said. “Following resolution of all concerns, the FNP was designated the Preferred Proponent and presented to Council for approval. As stated by the Auditor General, all technical requirements of the RFP were met.”

Michael Morgan was one of the five people on the Technical Evaluation Team in 2018. He was the City's director of rail operations at the time. The other team members include two egineering consultants: Lead Evaluator Peter Schwartzentruber and Jack D'Andrea; and two City officials: manager of rail systems Russ Hoas, and Colleen Connelly, OC Transpo's manager of service planning.

The Trillium Line extension, which moves the north-south line from Greenboro to the Airport and Riverside South, is currently under construction. It’s slated to be complete by 2022.
RELATED IMAGES

  • O-Train
    The Technical Evaluation Team noted SNC-Lavalin's bid included inaccurate references to an overhead catenary system on the Trillium Line, despite the trains being diesel-powered.
渥太华不会被这么一个破玩意儿拖垮吧
 
SNC-Lavalin's 'poor' LRT bid should have been tossed, evaluators found
Documents shed light on why city's own technical evaluation team failed company's Trillium Line bid

Joanne Chianello · CBC News · Posted: Jan 24, 2020 5:59 AM ET | Last Updated: 2 hours ago

o-train-ottawa-rail-transit-oc-transpo.jpg

Newly released documents shed light on why the technical evaluation team failed SNC-Lavalin's bid for the Trillium Line expansion. (Trevor Pritchard/CBC Ottawa)

SNC-Lavalin was awarded the $1.6-billion contract to extend Ottawa's north-south Trillium Line last March even though the team assembled to assess the bids reached a "unanimous consensus that the proposal should not be considered further in the evaluation process," according to documents released by the city Thursday night.

The SNC-Lavalin bid failed to include a signalling or train control system, had no plan for snow removal and, at one point, appeared to believe the trains that run on the Trillium Line were electric, not diesel.
The evaluation team concluded the bid was a "poor technical submission throughout," and that "resolving all of the major issues identified in the submission would be a lengthy and likely impractical process."

It was also critical of SNC-Lavalin for not being able to provide a plan for using the Trillium Line's existing fleet of Alstom LINT diesel trains in the future — something the other two finalists, Trillium Extension Alliance and Transit Link, were able to provide. The technical team called the omission a "fatal flaw."

On Oct. 3, the team concluded SNC-Lavalin's proposal "failed all four technical categories."

snc-lavalin-20191031.jpg

SNC-Lavalin Group Inc. won a $1.6-billion contract for the Trillium Line Stage 2 project, even though the technical evaluation team said they should be kicked out of the bidding. (Paul Chiasson/Canadian Press)

City executives used discretion
CBC Ottawa first reported back in March 2019 that SNC-Lavalin failed to meet the minimum technical score of 70 per cent that appeared to be required for a firm to continue in the competition, but still managed to win it.
In August 2019, the city finally admitted it was true. SNC-Lavalin had failed to score 70 per cent not just once, but twice: the company, operating under the name TransitNEXT, scored 63 per cent; the team was directed to rescore the bidders, but SNC-Lavalin still only scored 67 per cent.


A secret clause in the request for proposals (RFP) allowed the city's senior management team to wave a bidder onto the financial round, even if that bidder didn't score 70 per cent in the technical evaluation. The city's senior executive team exercised this discretion — without knowing the identity of the bidder, they say — following the advice of Geoff Gilbert, a Norton Rose Fulbright lawyer hired by the city to oversee the procurement of the contracts for LRT Stage 2.
Contrary to the technical evaluation team's advice, SNC-Lavalin's bid was allowed to move to the next phase of the evaluation process: the financial scoring. Because its bid was so much cheaper than its competitors, SNC-Lavalin was the put forward as the preferred proponent, and council approved the contract in
March 2019
.

Ottawa officials say the SNC-Lavalin bid offered taxpayers good value. And last November, the city's auditor-general found that the city had broken no rules in awarding the contract to the Montreal-based engineering giant.

geoffrey-gilbert-norton-rose-fulbright-at-ottawa-city-hall.JPG

Geoffrey Gilbert, centre, is a Norton Rose Fulbright lawyer who a member of the bid evaluation steering committee that directed the technical evaluation team to review its scoring. (Kate Porter/CBC)

Team asked to review score
Weeks after CBC Ottawa requested the technical evaluation team's presentation on its scoring, the city released them Thursday at 9 p.m., two hours after a marathon emergency meeting of the transit commission.

Although the city had already released the scores for SNC-Lavalin, the newly released documents shed light on what led the evaluation team to fail the company in two rounds of scoring.

On Oct. 3, the technical team presented its findings to the city's bid steering evaluation committee (BESC), a three-member team that oversaw the procurement for LRT Stage 2. The members of the committee included Gilbert, a Deloitte finance expert Remo Bucci and Simon Dupuis, a procurement officer for the city.

On Oct. 10, a different Norton Rose Fulbright lawyer — Martin Masse — called a meeting with the team and told them to review their scores based on numerous written questions from the BESC. The committee was concerned the evaluation team had considered details in its scoring that weren't explicitly asked for in the RFP.

ott-lrt-reaction_2500kbps_852x480_1582682179629.jpg


Diane Deans and Carol Anne Meehan say city councillors weren't given the information they needed before voting to approve the contract for Stage 2 of the LRT. 1:08

Bid lacked 'understanding'
After the technical team reviewed its evaluations, the scores of all three finalists rose slightly, but SNC-Lavalin still didn't make 70 per cent. And the evaluation team's responses to some of the BESC questions appear quite damning.

For example, BESC questioned the failing score for the systems integration management plan, which only required a "high-level description."

The technical team responded: "A high-level description should not include inaccurate information, such as references to elements that do not form part of the project scope of work, e.g. a catenary system, traction power substations … nor should it omit critical City tasks such as the integration of fare control equipment in the stations."

"Catenary systems" and "traction power substations" are parts of electric train systems — the Trillium Line is a diesel train system.

"This demonstrates that the proponent lacks understanding of the scope of [the] works," according to the evaluation team.

Among other glaring problems, according to the technical evaluation team, was SNC-Lavalin's complete lack of a train control system in its bid. The RFP did not demand that bidders provide a specific supplier of a train control system, but it did require "a narrative" of a "signalling and train control solution."

SNC-Lavalin gave no description of any kind of solution and stated only: "At the time of the technical submission we are still finalizing the option selection process."

ottawa-rail-construction-director-michael-morgan-lrt-oc-transpo-light-rail.jpg

Ottawa rail construction director Michael Morgan, right, was on the technical evaluation team that failed SNC-Lavalin's bid for the Trillium Line extension. (CBC)

 
拉完灵拉不完了咋地!
 
SNC没作弊,是价钱便宜,鹅市自己选的
不作弊哪来的便宜?预算不合理,维护费用飞涨。

现在一期就是这情况。下一次雪,它要是没出问题,一定是新闻,每天早晨都是哪站,哪段有毛病了,高峰期应当13辆车运行, 昨天是只有9辆车,今天是12辆。
 
。。。套路,先便宜拿下,然后维护保养上收钱
 
不作弊哪来的便宜?预算不合理,维护费用飞涨。

现在一期就是这情况。下一次雪,它要是没出问题,一定是新闻,每天早晨都是哪站,哪段有毛病了,高峰期应当13辆车运行, 昨天是只有9辆车,今天是12辆。


加拿大人到底有没有诚信啊?
 
他哪里是加拿大人,他就一大外宣的勤杂工,常发帖赚点小钱。
 
招标时候的条件不是每一箱都要达到。经常是驼子里面拔将军。预算放在那里了,一定要把钱花出去。
 
后退
顶部