- 注册
- 2002-10-07
- 消息
- 402,179
- 荣誉分数
- 76
- 声望点数
- 0
On Monday, March 30, Elgin Street northbound will close between Catherine and Nepean streets until approximately the end of July. This closure is required to facilitate the completion of the Elgin Street renewal project.
Workers will complete all sidewalks, parking bays, landscaping and tree planting, and install street furniture and public art. They will also add the final layer of asphalt.
Detours
All northbound motorists, cyclists and transit service will be detoured from Elgin Street. Access to local properties for northbound traffic will be from Metcalfe and Cartier streets.
OC Transpo Routes 5, 14 and 114 will be detoured away from Elgin Street in the northbound direction only. Bus stops currently on northbound Elgin Street will be relocated along the detour routes. Southbound buses will continue to serve Elgin Street.
Visit ottawa.ca and octranspo.com for more information.
Parking
On-street parking along Elgin Street and some side streets will be removed to accommodate the work. Please pay attention to on-street parking signage and restrictions.
Free parking is available at City Hall on weekday evenings from 6 pm until 6 am, and all day on weekends and statutory holidays.
Pedestrians
Pedestrian crossings will be maintained around the work and signed detours will be in place. A number of Elgin Street businesses remain open and access will be maintained at all times.
Stay informed
The project team would like to thank residents and businesses for their continued support and patience during this construction season.
Note: Measures will be taken on site to protect against the spread of COVID-19, including adequate hand washing, additional cleaning, sanitizing measures, and social distancing, among others. Understanding that the COVID-19 situation is rapidly evolving, the work plan is subject to change if the situation worsens or the contractor is directed to postpone construction activities. If this happens, it will be communicated to stakeholders and the public.
For more information on City programs and services, visit ottawa.ca or call 3-1-1 (TTY: 613-580-2401). You can also connect with us through Facebook, Twitter and Instagram.
查看原文...
Workers will complete all sidewalks, parking bays, landscaping and tree planting, and install street furniture and public art. They will also add the final layer of asphalt.
Detours
All northbound motorists, cyclists and transit service will be detoured from Elgin Street. Access to local properties for northbound traffic will be from Metcalfe and Cartier streets.
OC Transpo Routes 5, 14 and 114 will be detoured away from Elgin Street in the northbound direction only. Bus stops currently on northbound Elgin Street will be relocated along the detour routes. Southbound buses will continue to serve Elgin Street.
Visit ottawa.ca and octranspo.com for more information.
Parking
On-street parking along Elgin Street and some side streets will be removed to accommodate the work. Please pay attention to on-street parking signage and restrictions.
Free parking is available at City Hall on weekday evenings from 6 pm until 6 am, and all day on weekends and statutory holidays.
Pedestrians
Pedestrian crossings will be maintained around the work and signed detours will be in place. A number of Elgin Street businesses remain open and access will be maintained at all times.
Stay informed
- For information about the project, including up-to-date traffic impacts, visit ottawa.ca/elginstreet.
- Sign up for the Elgin Street renewal e-newsletter on ottawa.ca to get regular updates.
- Follow the City on social media:
- Twitter: @ottawacity
- Instagram: @cityofottawa
- Facebok: City of Ottawa / @cityofottawa
- Email the Elgin Street renewal project team at elgin@ottawa.ca.
- Listen to traffic reports from local news media.
The project team would like to thank residents and businesses for their continued support and patience during this construction season.
Note: Measures will be taken on site to protect against the spread of COVID-19, including adequate hand washing, additional cleaning, sanitizing measures, and social distancing, among others. Understanding that the COVID-19 situation is rapidly evolving, the work plan is subject to change if the situation worsens or the contractor is directed to postpone construction activities. If this happens, it will be communicated to stakeholders and the public.
For more information on City programs and services, visit ottawa.ca or call 3-1-1 (TTY: 613-580-2401). You can also connect with us through Facebook, Twitter and Instagram.
查看原文...