最初由 渐渐 发布
Cosmetic changes (i.e. installing hardwood floor) are done after framing. Your house is not at that stage yet.
This is the way new homes are built in this country. Your only other alternative is buy pre-fab homes, their homes are built indoors.
淋雨泡水了的木料确实让人担心,俺认为这种情况下压合板的好处就能体现出来了---不会一个方向曲张变形。最初由 SystemA 发布
Thanks!
The underneath of hard floor has stayed in water for several days in the framing stage. I worry that it would be abnormal after drying and impact on the above hardwood floor later, which is difficult to be found in the insepection of the new house.
Too bad RICHCRAFT!!
最初由 丫丫 发布
淋雨泡水了的木料确实让人担心,俺认为这种情况下压合板的好处就能体现出来了---不会一个方向曲张变形。
俺家的房子盖的时候也是夏天,当时雨季来的时候,别说木版,地下室的水泥地基里都存了水,当时俺也那个急啊,狠不得自己弄个小拖把去沾水
其实,这种盖房子方式已经是经过多年的考验,没有那么多问题了----比如,在房子完全密封前,只要连续一个星期的干燥天气,木料很快就干了。
就算复合板过些日子变形,你还有交房一年时的验收呢,到哪个时候,整个房子基本settle down,该出的问题就会出了,比如dry wall钉子会突起,有的dry wall 缝因为干燥变形不均匀显露出来,都是在一年验收的时候肯定会出现的问题。到那时候,地板变形,地砖裂缝都还是可以追究建筑商责任的。:glowface:
it take buider 6 month to buid the house,if it delayed 120 days, that is too long,my house only delayed 20 days.最初由 SystemA 发布
上回说道,我的新房子被延期了120天。很着急,多谢各位出主意。总算没事,现在是延期大约90天。
这两天我去工地看了看,一层和二层很快就钉好了。问题是外观看起来有些粗造。有些地方还漏着缝(1CM左右)。咱也不懂,这是否正常。昨天见了,BUIDER的老板,他说,主要是框子钉结实了就行了。其它不重要。真是这样吗?我们可以向他们提意见吗?结果会不会引起工人的反感,反而会更不好好干?
各位有没有这方面的经验,请指教!!谢谢先!