7.3 Project Phasing



As outlined in the Transportation Impact Study prepared by Delcan (December 21, 2011),

development of the proposed retail, restaurant, hotel, and office/industrial park uses is

expected to occur in three (3) phases over the period from 2015 to 2024.





 Phase 1, to be completed by 2015, consists of the 200-room hotel, four (4) 2,230

m2 (24,000 ft2) restaurants
, and the 31,587 m2 (340,000 ft2) retail outlet mall.





 Approximately 46,452 m2 (500,000 ft2) of office/industrial park space is planned

for Phase 2 (2019).





 Full build-out of the development (Phase 3), which includes an additional 46,452

m2 (500,000 ft2) of office/industrial park space, is planned to be completed by

2024.
 
Kanata的Outlet mall计划已经顺利通过审批,整个区域由3部分组成,3万1千多平方米的购物商场(90间店面),200间套房的酒店,还有4间各2千2百平米面积的餐馆,及9万3千平方米左右的商用办公园区。初步规划为3个施工阶段,第一阶段为酒店和购物商场完工时间2015年,然后为一半的商用办公园区完工时间2019年,剩下部分完工时间为2024年。
 
我敢肯定有个buffet,谁要搞?我入股啊
 
Kanata的Outlet mall计划已经顺利通过审批,整个区域由3部分组成,3万1千多平方米的购物商场(90间店面),200间套房的酒店,还有4间各2千2百平米面积的餐馆,及9万3千平方米左右的商用办公园区。初步规划为3个施工阶段,第一阶段为酒店和购物商场完工时间2015年,然后为一半的商用办公园区完工时间2019年,剩下部分完工时间为2024年。

只关心购物商场,2015年能建好,在加拿大这该表扬了。
 
后退
顶部